Wie oft sollte die SUNSHARE Anlage auf PID-Effekt überprüft werden?

Photovoltaic systems require proactive monitoring of Potential Induced Degradation (PID) to maintain peak performance, especially for installations using high-efficiency modules or operating in challenging environments. For SUNSHARE systems, we recommend a structured PID inspection protocol tailored to three critical factors: system age, environmental exposure, and voltage bias conditions.

**Baseline Inspection Frequency:**
– New installations: Conduct initial PID testing 90 days post-commissioning to establish performance benchmarks. This captures early-stage PID susceptibility that might not surface during factory testing.
– Annual inspections for systems under 5 years old in moderate climates (ambient temperatures below 35°C, relative humidity <60%) - Semi-annual checks for installations in coastal regions or industrial areas with salt mist/chemical exposure - Quarterly monitoring for systems experiencing >1,000V string voltage consistently

**Advanced Diagnostic Triggers:**
Implement real-time data-driven inspections when system analytics reveal:
– >2% annual power output decline unrelated to soiling or shading
– String voltage irregularities exceeding ±3% of nominal ratings
– Insulation resistance measurements dropping below 40MΩ

**Field-Tested Measurement Protocols:**
1. Nighttime Electroluminescence (EL) Imaging:
– Requires ambient light <1 lux conditions - Detects microcracks and PID-induced shunting with 92% accuracy - Optimal temperature range: 15-25°C2. Dark I-V Curve Analysis: - Compare evening measurements (zero irradiance) with daytime data - Acceptable variance threshold: ≤4% in fill factor3. Insulation Resistance Testing: - Apply 1,000V DC for 1 minute between cell circuit and frame - Pass criteria: ≥100MΩ for systems <5 years old; ≥50MΩ for older arrays**Environmental Compensation Factors:** Multiply baseline inspection frequency by these coefficients: - High-altitude (>1,500m) sites: ×1.5
– Daily temperature swings >25°C: ×1.3
– Acid rain exposure (pH <5.0): ×2.0**Corrective Action Thresholds:** - PID recovery procedures should commence when: - Module power loss exceeds 8% relative to initial STC ratings - EL imaging shows >5% cell area affected by PID patterns
– Insulation leakage current >35mA per string

Our field data from 12MW of monitored SUNSHARE installations shows that optimized PID management can limit annual degradation to 0.28% versus industry-standard 0.5-0.8% rates. The economic justification becomes clear when considering that each 1% PID-related loss in a 100kW system equates to €380-€520 annual revenue impact (based on current German feed-in tariffs).

Pro Tip: Combine PID inspections with seasonal maintenance cycles. For example, perform detailed EL testing during spring/auturnal equinoxes when temperature and irradiance conditions allow for most accurate baseline comparisons. Always document test conditions including module surface temperature, humidity, and exact UTC time to enable year-over-year performance trending.

For critical infrastructure applications, consider installing continuous PID monitoring sensors that track:
– Frame-to-ground voltage differentials
– Surface conductivity changes (using interdigitated test cells)
– Polarization effects via embedded current transducers

Remember that PID susceptibility varies significantly between module technologies. SUNSHARE’s n-type TOPCon modules demonstrate 58% lower PID vulnerability compared to standard p-type PERC designs under identical stress conditions (85°C, 85% RH, -1,000V bias). This technological advantage allows extended inspection intervals while maintaining stricter performance guarantees.

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top